Challenge: With existing utilities, a busy highway, and duel 88" vertical bores going under Business I-95 in Fayetteville, a shoring solution was needed that could support a 20'x40' pit where workers could safely pour a concrete pad and set lag bolts.
Solution: MSP Rents deployed a special shoring solution called a Slide Rail system. First the corner posts were set, then a rail, and then the panels - all working together to provide shoring as the hole was being created. This system kept the workers safe, existing structures secure, and productivity levels high.